Monday, August 29, 2016

Getting the Heat On.

Yes, Im going a little out of order here.  Sharp eyed readers will notice the sand blasting was done after the HVAC was installed.  I forgot.  Sue me.

Local Shawnee Kansas HVAC company KB Complete gave us a great bid on the 3 different HVAC systems.  We have a small 4 ton system for the warehouse, an 8 ton package rooftop unit for the bullpen area and a Mitsubishi mini split system with 3 heads to take care of the kitchen, patient training area and AJ's office.  The best of all worlds I suppose.


Warehouse unit.


Hanging the spiral duct.
 

 

 Harold, Kenny, and the guys came in and got started hanging the systems well out of the way of daily operations.  They were amazingly understanding with our long schedule and came in over the course of 6 months to get things installed as we got different phases completed.



Package unit hoisted to the roof.
Suitcase unit for the mini splits.